THE PIT DESIGN PLANNING AND PLANNING RESULT EVALUATION OF OVERBURDEN FRONT FROM WEST TO EAST USING MINESCAPE VERSION 5.7 SOFTWARE AT PT XYZ

Authors

  • Roby Cahyadi Atma Jaya Catholic University of Indonesia
  • Isdaryanto Iskandar Atma Jaya Catholic University of Indonesia
  • Diansah Aprianto Akamigas Palembang of Polytechnic, Indonesia

DOI:

https://doi.org/10.53625/ijss.v2i4.4241

Keywords:

Minescape, Design, Calculation, Overburden

Abstract

PT XYZ is a private company managed by foreign company was engaged in coal mining sector located in Muara Enim, South Sumatera. This company conducts open mining system or surface mining. The overburden volume production calculation applied by PT XYZ used software that is Minescape 5.7. Software. The objectives of this research was creating a front design of overburden from west to cast with elevation of #10 to 0 and the calculation of cut and fill volume of overburden planning and the joint result used Minescape 57. Software, comparing the amount of cut and fills volume and determining the factors causing the difference of the overburden volume calculation using Minescape 5.7. Software. The method used was material stockpiling method and disposal stability became the author's basis to recommend a disposal in pit which can accommodate safe product to be implemented in the field. Based on the calculation results using Minescape 5.7. Software in May, the obtained overburden volume was 587.36 BCM. From the analysis results related to the Minescape 5.7. Software calculation comparison between the progress and the joint of the cut was 428.62 and the fill was 20.48.

References

Bargawa, Waterman Sulistyana. 2018 Mine Planning. Yogyakarta: Gadjah Mada University Press.

Darrumidi, sports. 2011. Geological Mapping Guide to Praction for Beginner Geologists. Yogyakarta: Gadjah Mada University Press.

Fadli, Sri Widodo, 2015. Block C Coal Mining Pit Design. Geomine Journal. 03(02), pp. 14-15.

Hadi, Nugroho MS 2013. Soil Measurement. Ministry of Education and Culture of the Republic of Indonesia: Jakarta.

Hamzah, Yusuf. 2020. Survey and Mapping. Yogyakarta: CV Budi Utama Publisher Group.

M.AJ, Martadinata, Sepriadi. 2019. Coal Pit Design Modeling Using Minescape Software 4.11.8. Academic Engineering Journal. 10 (01), P. 83-84.

Young, Alexander. 2008 Survey and Mapping Techniques. Jakarta: Directorate of Vocational High School Development.

R.and Erwin Wijaya, 2015. Hollow Limestone Quarry Mine Design in the Sawir Block, Tuban, East Java. Promine's Journal. 03(02), P.12-13.

Sudrajat, Nandang. 2013. Indonesian Mining Theory and Practice. Yogyakarta: Yustisia Library.

Tian'an Technology Zone. 2017. Hi-Target Surveying Instrument Co., Ltd. China: Indosurta Group.

Downloads

Published

2022-12-10

How to Cite

Cahyadi, R., Iskandar, I., & Aprianto, D. (2022). THE PIT DESIGN PLANNING AND PLANNING RESULT EVALUATION OF OVERBURDEN FRONT FROM WEST TO EAST USING MINESCAPE VERSION 5.7 SOFTWARE AT PT XYZ. International Journal of Social Science, 2(4), 1959–1968. https://doi.org/10.53625/ijss.v2i4.4241

Issue

Section

Articles